Steel barns and steel greenhouses: planning and cost items
Both are agricultural production buildings, both are built from galvanized steel, and in both, what really matters is not the structure itself but the climate inside it. This article lists the items to pin down before you get a quote.
Why is galvanizing non-negotiable for both?
Painted steel lasts many years without problems in a dry, enclosed space. The inside of a barn or a greenhouse does not fit that description: both have constantly high humidity, plus ammonia and contact with manure in a barn, and condensation collecting directly on the sections in a greenhouse.
Under these conditions, paint breaks down at joints, bolt holes and scratches; corrosion starts there and usually spreads where no one can see it. Hot-dip galvanizing is the deciding item here because it provides cathodic protection even at cut and scratched points.
Galvanizing is also a separate stage that has to be added to the schedule — once workshop fabrication is finished, the parts go out for galvanizing and come back, and only then does installation take place. This should not be forgotten when the lead time is worked out.
The ends of closed sections are always capped. An open section end lets rain and condensation inside; corrosion then starts from within and gives no sign on the outside.
Planning a barn: it starts with head count, not square meters
The size of a barn is derived from the number of animals. Area per animal, feed bunk length, number of waterers and stall size are set according to the breed and the way the farm is run; the building’s width and length follow from these needs.
Next, the farm’s traffic flow is mapped out, and this determines the column layout: where the feed vehicle will come in, which line the manure scraper will run along, which route the animals will take to milking. A column that lands on one of these lines is a nuisance every day and cannot be removed later.
The third decision is climate, and it determines the building’s orientation. The prevailing wind direction affects how much of the side walls stays open and how wide the ridge opening is. That is why taking a barn design that works well in another province and reusing it unchanged often ruins the ventilation.
Planning a greenhouse: it starts with the crop
In a greenhouse, the first thing to settle is the crop, because the crop determines the trellis-wire height and therefore the side wall height. Row spacing and access paths determine the internal layout, and that in turn determines the span.
The second, often overlooked item is the hanging crop load. With crops such as tomatoes, cucumbers and peppers, the plants are hung from the frame, and this is a permanent load measured in tons per decare (1000 m²). When this load is left out of the calculation, the problem shows up in the first harvest season as the frame visibly flexes. Telling us at the start what you will grow directly changes the choice of sections.
The third is orientation: the long axis of the greenhouse affects how light is distributed through the day and how the prevailing wind acts on the structure. In wind, the deciding force on a greenhouse is not horizontal push but uplift — the anchoring’s main job is to hold the structure down.
Cost items: what to ask to get a clear quote
For both buildings, asking “how much per decare?” or “how much per square meter?” does not by itself produce a meaningful answer, because building the same area with a different span and a different load changes the total noticeably. Once the items below are clear, quotes become comparable.
Span
The distance to be bridged without columns. In both, the first item that determines section sizes and tonnage.
Loads
Snow and wind for a barn; for a greenhouse, the hanging crop load on top of these. The region and the crop together determine these loads.
Surface treatment
The scope of hot-dip galvanizing — the whole structure, or only certain parts?
Cladding / covering
Trapezoidal sheet or sandwich panel for a barn; PE film, polycarbonate or glass for a greenhouse. Each is a different class.
Ventilation
The ridge and side wall details for a barn; the number of roof vents and the opening mechanism (manual / motorized) for a greenhouse.
Ground and anchoring
Floor concrete and a manure channel for a barn; concrete socket footings or screw piles for a greenhouse, depending on the soil.
Equipment
Stalls, feed bunks and partitions for a barn; benches, irrigation and heating lines for a greenhouse. These are separate items from the structure.
Tell us your growth plans today
Both buildings can be extended later, but whether that is cheap depends on whether it was planned from the start. In a building designed to be extended, the new section sits on the continuation of the existing grid, and the end frames are chosen to take that load.
This is particularly easy with a multi-span greenhouse: the new span is added as a continuation of the existing gutter line. With a tunnel greenhouse, it usually makes more sense to add a new tunnel. On a barn, an extension has to be positioned so that it does not disrupt the existing ventilation flow — a section added in the wrong place cuts off the airflow of the existing barn.
Mentioning the possibility of growth during the site survey adds very little to today’s cost; not mentioning it may mean having to strengthen part of the existing structure when you extend.
Permits and subsidies: the part we can’t answer for you
Both buildings are subject to zoning and agricultural building regulations; for barns, there are also rules on area per animal and ventilation. For greenhouses, agricultural support programs may come into play.
We cannot give definitive information on these matters, and we don’t try to — you need to confirm with the municipality and the provincial directorate of agriculture. What we provide is the structural calculation and the construction drawings; we prepare the technical documents required for applications.
When getting a quote, ask specifically whether the galvanizing process is included in the schedule and whether foundation and floor work is within the scope. It is common for both items to surface later.
Water management: the weakest point of both buildings
In barns and greenhouses, most deterioration comes from water, and the water comes from three separate sources: rain, condensation and the operation’s own water.
Rainwater runs from the roof into the gutters and from there into the downspouts. When this line gets blocked, water gets under the covering and reaches the structure. The gutter line in a multi-span greenhouse, and the eave and ridge joints in a barn, are the most critical points. A cleanout in late fall prevents most of the problems you would otherwise face all winter.
Condensation is a deciding factor in greenhouses in particular: warm, humid inside air condenses on cold surfaces and drips. If the drips fall on the plants, they create a disease risk; if they collect on the sections, they speed up corrosion. The right slope and a condensation channel direct it away.
Operational water means cleaning and manure scraping in a barn, and irrigation in a greenhouse. If the floor slope and the channel line are not drawn together with the structural grid, the column bases stay wet all the time — even when galvanized, that becomes the point that wears fastest.
Keeping column bases free of soil and making sure water does not pool around them is the cheapest way to extend the life of either building.
Annual maintenance calendar
Both buildings are low-maintenance, but not maintenance-free. The calendar below is the sequence we have seen work best in the field.
Late fall
Clean the eaves gutters, valley gutters and downspouts. In a barn, clear the dust and straw that has built up in the ridge opening — a blocked vent keeps moisture inside all winter.
Late winter
After snow loads, look for any visible deflection or deformation in the structure. In a greenhouse, check the tension of the covering and its fixings.
End of the first season (once only)
Have the torque on the bolted connections checked. It is normal for a few bolts to loosen as the structure settles after installation, and this is corrected early on.
Once a year, by eye
Surfaces at animal contact height, the column bases and the ends of closed sections. Touch up any spots where the paint has come off or that show impact damage.
Pages related to this article
- Steel BarnsWide-span barns designed around ventilation and hygiene.
- Steel GreenhousesGreenhouse frames in galvanized profiles, built to withstand wind and snow loads.
- Steel ConstructionStructural steel systems for warehouses, workshops and commercial buildings.
- Steel RoofsComplete roof structures, with purlins, trusses and roofing.
Let’s talk about your project
This article covers general cases; your entrance, plot or building comes with its own constraints. Send us measurements and photos, and we’ll tell you which solution fits.